Roadworks along TF-82

The works will consist of the cleaning, cutting and removal of vegetation and loose material

27 june 2023

 On July 3, the work of clearing slopes along the TF-82 PK 46 + 770 will begin.

The works will consist of the cleaning, cutting and removal of vegetation and loose material, clearing of unstable blocks that may be at risk of detachment and the removal of the disused culvert at the top of the slope, as well as the aerial tube that crosses the road. All work will be carried out by personnel specialised in vertical work.
The work is scheduled to last for 4 days.   Once the cleaning is finished, wet pre-concreting will be carried out by spraying concrete with a minimum resistance of 25 N/mm2 at compression with average thicknesses of 6 cm. The duration of these works will be 1 day.
Subsequently, a triple twist galvanized steel lattice of type 8x10-16 will be placed. The expected duration of these works will be 4 days, and the plan is to carry out the work whenever possible with alternative traffic. The zone will be cemented too.
To carry out the works it will be necessary to cut the TF-82 between PP.KK 46 + 550 to 47 + 050 completely at certain times. The plan is to carry out the bulk of the work during daytime (from 08:00 hours to 16:00 hours). For traffic cuts and diversions, the necessary marking and signalling will be in place.